PPL Electric Utilities requirements for the provisions of the FCC Order 18-111.
The effective date of Federal Communications Commission's (FCC's) Order 18-111 is May 20, 2019. For detailed information regarding the Order, please refer to the FCC's Third Report and Order and Declaratory Ruling released on August 3, 2018.
One-Touch Make-Ready
One-Touch Make-Ready (OTMR) is "simple" communications space work. Simple communications space make-ready involves rearranging communication space cables where there is no reasonable expectation of a service outage or facility damage, no cable splicing and no antennas. If power space make-ready work or work above the communications space is required, OTMR may be applied only after all power space make-ready work is complete.
PPL Electric Utilities contractor requirements for OTMR:
A requesting attaching company must use one of the following approved contractors to complete the OTMR survey work:
A requesting attaching company must use one of the following approved contractors to complete the OTMR construction work in the communications space:
PPL Electric Utilities requirements for OTMR:
-
New attacher can bifurcate work associated with a project on a single application; ; identifying no make-ready work poles, poles with OTMR communication space only make-ready work, and poles with power space make-ready work.
- The date and time of the make-ready construction work.
- A description of the make-ready work involved.
- A reasonable opportunity to be present when the make-ready work is being performed.
- The name of the contractor chosen by the new attacher to perform make-ready work.